Preventive Generation Maintenance Scheduling with Network Constraints, Spinning Reserve, and Forced Outage Rate
- Faculty of Electrical and Computer Engineering, Babol University Technology, Babol, & Shahid Rajaee Teacher Training University, Tehran
- Department of Electrical and Computer Engineering, Shahid Rajayee University
Published in Issue 2024-02-25
How to Cite
Norozpour Niazi, A., Badri, A., & Sheikhol-Eslami, A. (2024). Preventive Generation Maintenance Scheduling with Network Constraints, Spinning Reserve, and Forced Outage Rate. Majlesi Journal of Electrical Engineering, 7(1). https://oiccpress.com/mjee/article/view/5232
HTML views: 14
Abstract
The completely Electric Power System encompass three parts: Generation, Transmission, and Distribution that all require maintenance to better system reliability and energy efficiency. Most generation maintenance scheduling (GMS) packages consider preventive maintenance scheduling for generating units over one or two year's time horizon to lessen the total operation costs while fulfilling system energy requirements. In advanced power systems, The inclusion of network limitations, reserve index, forced outage rates of the units and demand for electricity have highly increased with related expansions in system size, which have led to higher number of generators and lower reserve margins making the generator maintenance scheduling problem more complex.é 鲿§ç¶è·çæèèª¿åº¦ç¶²çµ¡ç´æï¼æè½åç¨ï¼ä¸¦å¼·è¿«åéçæè¦å®å¨é»åç³»çµ±åæ¬ä¸åé¨åï¼ç¼é»ï¼è¼¸é»ï¼éé»ï¼ææéè¦ç¶è·ï¼ä»¥æ´å¥½å°ç³»çµ±çå¯é æ§åè½æºæçãææ°ä¸ä»£ç¶è·è¨åï¼GMSï¼å°è£èæ®é 鲿§ç¶ä¿®èª¿åº¦ç¼é»æ©çµå¨ä¸å¹´æå©å¹´çæé跨度ï¼ä»¥æ¸å°ç¸½éçææ¬çåæå¯¦ç¾ç³»çµ±è½éè¦æ±ãå¨åé²çåå系統ï¼ç¶²çµ¡éå¶ï¼å²åææ¸åå¥ï¼æéå®ä½åé»åéæ±çå¼·è¿«åéçé«åº¦è系統ç大å°ç¸éçæ´å±ï¼éäºé½å°è´äºè¼é«çæ¸åç¼çå¨åä¸èª¿æºåé婿½¤ç使å¾ç¼é»æ©ç¶ä¿®å¢å 調度å顿´å è¤éãKeywords
- Forced Outage Rate.,
- Maintenance Scheduling,
- Network Constraint,
- System Reserve