Sustainable and renewable are certainly very appreciated terms nowadays. These words may summarize a whole new attitude towards our world and the people who live in it. This paper’s goal is to define an original multi-criteria energy model, named SRIME, specially designed for developing countries. First, an extensive research will be carried out on: energy demand; potential renewable energy, its current know-how and potential future development; potential avoided emissions (CO 2 , NO X , SO 2 ); and the possible international support versus the in-country possibilities. The precedence constraints will be applied to establish in which degree renewable energy may be substituting for the fossil fuel: the purely economic approach will give way to a sustainable, renewable, development focused energy planning. It must be noted that an innovative function has been specifically included in the SRIME, which evaluates, applying the precedence constraints, the influence renewable energy may have on developing countries rural health and education. Six functions have been established: replaceable amount of fossil energy; CO 2 , NO X and SO 2 avoidable emissions; rural health and education development maximization; and the cost function. These functions will be optimized through the Chebyshev distance ( L ∞ ) compromise programming minimization, so that the Pareto optimal solution may be obtained.
The MCDM has been used over the years [ 1 , 2 ], and is indeed a currently widely used tool for energy applications [ 3 – 6 ]. The aim of this paper is to focus on a set of sustainable and renewable factors that will be assessed through a precedence constraints evaluation. The optimal solution will be then chosen among the possible solutions for every one of the six equations, applying the Linear Programming Computation (LPC). The best compromised solution is then found among the Pareto optimal solutions [ 7 ], which will allow rejection of the solutions corresponding to any of the six optimizing equations that are found to be situated furthest from the rest of the optimal values obtained for the remaining equations. This way the dominating solutions will be softened, letting energy planners base their decisions on a solution that can not be improved without making at least one of the variables worse off.
This method’s greatest challenge is how investigators and then planners will decide to calculate the weights to be applied to every one of the six equations. This decision will require a broad consensus among a wide range of experts so that decisions are not postponed, generating conflict, wasting time and, therefore, damaging future programming.
The subjective part of the compromise programming is also a demanding issue, which has to be carefully and professionally performed. The value given to the different subjects must be thoroughly assessed, avoiding a personal opinionated view from the experts.
Figure
1
shows the steps that are proposed in this model, which has been specifically designed for low materially developed countries. The first stage is to carry out a thorough evaluation of the current energy demand, and subsequent future needs. Secondly, the possible renewable solutions will be assessed, taking into account the in-country possibilities, along with the international support, aiming to enunciate the first function, using the precedence constraints.
1
The third step will be to study the potentially avoidable emissions so that the corresponding three functions may be stated (
F
2
,
F
3
,
F
4
). Then the fifth function will come from a deep study of the possible interactions between health and education and renewable energy, according to the parameters described by the UN and other international organizations. The last phase is to enunciate the cost function (
F
6
).
SRIME energy model. Own constructionFig. 1

The L k distances will then be minimized, according to the chosen weights, so that a compromised solution may be selected among the several obtained by the preferred optimization tool. 2
The so-called green economy focuses on the various advantages our world shall enjoy if we were to go green [
8
–
11
]. Not only climate change is involved here but also the potential enhancement of the overall development factors, especially the health co-benefits. You may find the corresponding equation and Table
1
below, which includes a summary of the potential precedence constraints the authors have chosen to be applied [
12
–
14
].
3
Precedence constraints Technological factors Application Energy planning Fossil fuel environmental impact Technological demand Operating time Political interest Fossil fuel environmental impact Potential investigation Implementation issues Current price compared with conventional energies Know-how up-to-date Integration possibility Social demand Technology improvement (possibly locally manufactured equipment) Potential demand Legislative forecast Current technological level to apply the alternative energy Supply availabilityTable 1
Environmental impact has ben a major concern in the world for the past ten years. Local researchers are indeed looking into potential present and future sustainable possibilities [ 15 , 16 ].
These are the three corresponding functions:
B ij / C ij / D ij : life cycle CO 2 /NO x /SO 2 avoided emissions (ton/energy unit)
For all B ij ≥ 0; C ij ≥ 0; D ij ≥ 0 ⇒ max F 2 ; F 3 ; F 4 ⇒ optimal avoided emissions maximization
Coefficients B ij , C ij , D ij are obtained from official statistics and specialized publications.
One of the most usual indicators to estimate energy demand is the GDP growth rate. LEC and LRY commonly enjoy a high degree of causality. However, while HMDP show a bidirectional causality, LMDP only dictate a uni-directional causality from LRY to LEC [
17
]. As you can see below in Fig.
2
, this is confirmed by the SL official data.
SL expenditure vs energy consumption. Prepared by the authors based on official data [
18
–
23
]Fig. 2

This is the corresponding equation:
Coefficients E ij are non-dimensional and obtained through precedence constraints, where no energy or cost quantification is involved. These precedence constraints are based on:
Identified health and education ad-hoc applications.
Low overnight capital cost/unnecessary donor support for health and education enhancing applications.
Low maintenance cost.
Unnecessary maintenance contract.
Long lasting systems for health and education purposes.
Short distance from health and education centres to energy source.
Safe from being stolen in rural environment.
Low rural environmental impact.
Predictability.
Batteries not required for health and education purposes.
Alternating current.
Possible modularity/size accommodation for schools and hospitals.
Added benefits for rural development.
In-country development: manufacturing, training, etc.
Low LEC.
Hospitals and schools space efficiency for rural development.
Low or inexistent waste generation.
This function can also consider the renewable energy subsidies, therefore affecting the C coefficients. Another possibility can be to modify the coefficients, aiming to reach the best possible subsidy for every RE.
As per coefficients B ij , C ij and D ij , coefficients G ij are also obtained from official sources.
The restrictions to be applied are described below in Table
2
, having in mind the following [
1
,
3
,
12
and own construction]:
Restrictions Non-electric energy use Electric energy use RE potential production Current RE systemsa Energy demand of application
j
, calculated as:
S
j
=
p
j
−
i
j
; where
p
j
is the energy demand corresponding to sector
j
and
i
j
is the amount of fossil fuel renewable sources can not replace. Energy demand of application
i
, calculated as:
S
e
=
p
e
−
i
e
; where
p
e
is the energy demand corresponding to sector
e
and
i
e.
is the amount of fossil fuel renewable sources can not replace. Potential application of renewable source
i
in the corresponding sector. Minimum amount of conventional energy renewable sources can replace, as RE has already replaced this amount.Table 2
As indicated by Linares et al. [
24
–
26
], to obtain the set of compromised solutions, both the normalized Manhattan distance,
L
1
or the Chebyshev distance,
L
∞
, may be minimized [
27
,
28
]. Nonetheless,
L
k
will also help us obtain the optimal solution. Equation (11) below shows the general definition for
L
d
. Equations (12), (13) and (14) show the normalization to be carried out and Table
3
the distances that must be minimized.
Normalized distances to be minimizedTable 3
Taking into account that
W
i
is the weight or preference assigned by the decision makers, the distances to be minimized may be found below in Table
4
.
Restrictions summary Distance RestrictionsTable 4
The authors have prepared a sectorial energy consumption forecast for 2015 (see Table
5
; Fig.
3
) and the estimated generation and capacity mix (see Figs.
4
,
5
). The global electricity data has been obtained from the Long Term Generation Expansion Plan 2013–2032, prepared by the Ceylon Electricity Board, and the rest of he energy consumption and the electricity sectorial data has been estimated by the authors based, on official and private documentation [
29
–
50
].
2015 SL sectorial energy consumption forecast (ktoe) [
29
–
50
] Electricity LPG Gasoline Naphta Avgas Kerosene Avtur Diesel Foil Coal Bagasse Fwood Agriculture 3.1 8.6 Industries 372.4 36 25.1 85.6 180.7 83 65.1 1961 Transport 1.8 981.8 2.7 0.2 486.5 1924 2.7 Education 3.9 Religious 6.7 HH 428.6 105.4 143.1 3739.2 Hotels 20.9 1.9 8.3 Street light 14.6 Health 15.7 1.2 2.4 Commercial 236.1 137.1 15.3 14.7 13.8 427.8 2015 Sri Lanka sectorial energy consumption forecast [
29
–
50
]Table 5
Fig. 3

Fig. 4

Fig. 5

SL is very much dependent on petroleum, which currently accounts for approximately 24 % of SL import bill and 45 % of exports. The demand has been doubled, in value terms, during the last 3 years [ 52 ]. The geo-climatic settings are particularly conducive, though, to harnessing hydro resources. The climate is largely determined by the meteorological conditions caused in the Indian sub continent due to the tropical circulation [ 53 ]. The current hydro power stations are operated to meet both peak and base electricity generation requirements. A 400 MW potential has been identified for small hydropower projects [ 54 ], typically characterised with less than 10 MW capacities [ 53 ]. 128 projects, totalling 271 MW, have been already commissioned as of 31/12/2014 [ 55 ]. Once these projects are available for power generation, will be carefully followed-up by PUCSL [ 56 ]. In terms of wind power, GOSL would like to go from the current 5 % to reach 10 % by 2017 and 14.1 % by 2022 [ 56 ]. There are close to 500 km 2 of windy areas with good-to-excellent wind resource potential. However, only a portion of this is deemed feasible to be harnessed because of technical and system limitations [ 57 ]. As of 31/12/2013, there are 10 commissioned projects, which will add 78.45 MW capacity to the grid [ 55 ] and also some possible future WPPs [ 58 – 61 ]. The wind potential has been estimated as 20,000 MW. In terms of biomass, Gliricidia sepium has been recently appointed as the fourth plantation crop after tea, rubber and coconut. Biomass application in electricity generation is not yet widespread, but it is gaining momentum [ 54 ]. As of 31/12/2014, 2 Agricultural and Industrial Waste Power projects have been commissioned (11 MW); and another 2 Dendro Power (5.5 MW) [ 55 ]. A 1000 MW of Dendro thermal potential has been estimated [ 59 ]. Biofuels are also planned to be developed to claim a 20 per cent share by 2020 [ 58 , 62 ]. Although the village biogas power is at an early stage, as it has not been an easy task to introduce it [ 63 , 64 ], there are indeed a number of projects going on. This NCRE seems to be following the increasing tendency currently shown in South Asia [ 59 ]. A 300 MW MSW biogas generation potential has been identified [ 65 ].
As showed on Table
6
above, the use of SHSs has been spreading fast in the rural areas of Sri Lanka, mainly because of the financial incentives provided by the donor agencies, and also due to the aggressive marketing strategies of the SHS dealers in rural areas [
66
,
67
]. As of 31/12/2013, 4 solar projects have been commissioned, totalling 1,4 MW. As of 31/12/2012, the installed PV capacity was 10.10 MWp [
68
]. Concerning geothermal energy resources, SL is still at a preliminary stage, although a 700–1300 MWe potential has been recently estimated. As a first step in the development, a USD 10 M investment would cover a site selection study, surface exploration at the most promising site followed by deep drilling, and commissioning of a 2 MW binary power plant if the wells are successful [
69
]. Regarding off-grid schemes, a pilot project was recently conducted to connect two village micro hydro power plants (10 and 20 kW) to the national grid. This pilot project has become instrumental in removing the technical, social, and legal barriers for grid interconnection. It is necessary, though, to review these fees structure and try to reduce them, taking into account the capacity of the project [
70
] and the potential funding [
71
–
73
]. The overall target for NCRE is to reach 10 % by 2016 and 20 % by 2020 [
63
]. Some authors are praising SLs NCRE implementation [
64
], while others believe that lack of financing instruments, along with high initial cost and lack of assurance of resource supply or availability are the main barriers for renewable technologies expansion in SL [
65
,
66
]. Reaching the above mentioned targets is not just an environmental matter, but are related in one way or another to at least five other MDG [
67
,
74
]:
2012 status of Sri Lanka off-grid energy technologies Technology Number of units installed Capacity of a unit (KW) Estimated total capacity (MW) Number of households electrified Number of units still in use (estimated) Solar home systems (PV) 120,000 0.03–0.06 3.6 120,000 100,000 Village micro hydro power 300 3–50 4.5 10,500 80 Village dendro power 11 10–30 0.1 100 – Wind home systems 30 0.25–3.0 0.007 30 – Village biogas power 10 0.3–2.0 0.006 30 2 Pico hydro power 40 0.3–1.5 0.012 40 40 Total 8.2 130,700Table 6
Eradicate extreme poverty and hunger.
Achieve universal primary education.
Gender equality and empowering women.
Reduce child mortality.
Improve maternal health.
Taking into account all of the above, the authors have estimated that the following energy is considered to be substitutable in 2015 (see below Table
7
).
Substitutable energy in 2015 (ktoe) Electricity LPG Gasoline Naphta Avgas Kerosene Avtur Diesel Foil Coal Bagasse Fwood Agriculture 0.5 1.3 Industries 74.5 12.8 27.1 Transport 147.3 288.6 0.4 Education 0.8 Religious 1.3 HH 85.7 Hotels 4.2 1.2 Street light 2.9 Health 3.1 0.4 Commercial 47.2 2.2 2.1Table 7
The authors have defined the following variables:
BT I : biomass thermal, industrial.
BT H : biomass thermal, household.
BT HE : biomass thermal, health.
BT C : biomass thermal, commercial.
LBF A : liquid biofuel, agriculture.
LBF T : liquid biofuel, transport.
SH: small hydro.
WPP: wind power plant.
BEG: biomass for electricity generation.
PV: photovoltaic electricity generation.
MSW: municipal solid waste.
The restrictions for this case study have been established by the authors as per below:
A: Based on energy demand and RE real potential (in ktoe):
LBF A ≤ 1.8
BT I ≤ 2148.9
LBF T ≤ 436.3
BT H ≤ 1.2
BT HE ≤ 0.4
BT C ≤ 432.1
Electricity 4 :
SH ≤ 150
PV ≤ 30
WPP ≤ 100
MSW ≤ 100
BEG ≤ 60
B: Based on the already existing RE (in ktoe):
LBF A , LBF T ≥ 0
BT I ≥ 2109 5
BT H ≥ 0
BT HE ≥ 0
BT C ≥ 427.8
SH ≥ 47.3
PV ≥ 3.6
WPP ≥ 8.6
MSW ≥ 0
BEG ≥ 15.1
To determine the coefficients corresponding to function
F
1
, the authors have established the precedence constraints included below in Table
8
.
BEG BT LBF MSW PV SH WPP Technological demand 2 2 2 3 4 5 3 Potential investigation 5 5 5 5 5 4 5 Know-how up-to-date 4 5 3 4 4 3 5 Technology improvement (possibly locally manufactured equipment) 3 3 3 3 3 3 2 Current technological level to apply the alternative energy 2 3 2 2 4 Operating time 3 5 2 3 3 4 2 Implementation issues 3 5 2 3 3 5 3 Integration possibility 5 5 5 5 5 5 5 Potential demand 2 2 2 4 4 5 4 Supply availability 3 3 2 4 4 4 4 Political interest 2 2 2 3 3 5 4 Current price compared with conventional energies 1 2 2 1 2 5 3 Social demand 1 2 1 2 2 5 2 Legislative forecast 3 3 3 3 3 3 3 Environmental impact 5 3 5 5 5 5 5Table 8
The following values are then calculated (see Table
9
below):
Calculation of
N
and
M
factors Alternative Coefficient SH 216 3.4 × 109 2.5 WPP 82,944 108 2.5 PV 186,624 9 × 107 2 BT 248,832 2.4 × 107 2 MSW 466,560 2.3 × 107 2 BEG 3.1 × 106 1.9 × 106 1.5 LBF 8,847,360 864,000 1Table 9
Once the coefficients are applied, this is the final equation for F 1 :
F 1 = 2.5 SH + 2.5 WPP + 2 PV + 2 BT I + 2 BT H + 2 BT HE + 2 BT C + 2 MSW + 1.5 BEG + LBF A + LBF T
CEB expected generation system for 2015 [
20
] has been taken into account (see below Table
10
) to establish the potentially avoided emissions. According to the different types of fuel and their corresponding GWh in 2015, a 9.9 tCO
2
/toe weighted average will be considered as the amount of avoided emission as well as 0.028 tNO
x
/toe and 0.041 tSO
2
/toe [
20
,
104
–
114
].
Generation forecast data from the Long Term Generation Expansion Plan 2013–2032, prepared by the CEB [
20
] Capacity balance (MW) Energy balance (GWh) 2013 2014 2015 2013 2014 2015 Plant name Hydro Existing major hydro 1335 1335 1335 4112 4112 4112 New major hydro 0 0 0 0 0 0 Mini hydro 219 232 244 – – – Sub total 1554 1567 1579 4112 4112 4112 NCRE-wind 90 90 90 – – – NCRE-solar 1.3 21 31 – – – Total NCRE 613 658 692 Thermal existing and committed Small gas turbines 85 85 85 16 6 4 Diesel Sapugaskanda 72 72 72 459 431 456 Diesel ext. Sapugaskanda 72 72 72 491 485 487 Gas turbine no 7 115 115 115 290 250 286 Lakdhanavi 0 0 0 0 0 0 Asia power 49 49 49 334 309 332 KPS combined cycle 165 165 165 550 454 549 AES combined cycle 163 163 163 491 362 474 Colombo power 60 60 0 419 417 0 ACE power Horona 0 0 0 0 0 0 Ace power Matara 0 0 0 0 0 0 Heladhanavi 100 100 0 696 696 0 ACE power Embilipitiya 100 100 0 692 672 0 Biomass (Dendro) 10 10 10 94 94 94 Kerawalapitiya 270 270 270 1325 935 1138 Puttalam coal 275 550 825 1665 3241 4996 Northern power 0 20 20 0 131 137 Chunnakkam power extension 0 24 24 0 183 183 Sub total 1535 1854 1870 7523 8668 9135 New thermal plants Coal 0 0 0 0 0 0 Gas turbine 75 MW 0 0 225 0 0 477 Gas turbine 105 MW 0 0 0 0 0 0 Coal trinco 0 0 0 0 0 0 Biomass (Dendro) 4 8 12 27 54 82 Sub total 4 8 237 27 54 559 Total installed capacity 3184 3540 3807 – – – Installed capacity without NCREa 2874 3197 3442 – – – Peak demand 2451 2692 2894 – – – Difference without NCREa 423 505 548 – – – Difference (%) 17.3 18.8 18.9 – – – Total generation – – – 12,275 13,493 14,499 System demand – – – 12,296 13,508 14,513 Unserved energy 21 15 14Table 10
You can find below Table 11 , which includes a summary of the life cycle emissions corresponding to the different types of renewable energy, based on the below mentioned references.
In terms of LBF, 90 % of the CO 2 emissions are considered to be potentially avoided [ 122 – 124 ] that is, approximately 2.7 tCO 2 /toe. When biofuel replaces gasoline and diesel in the transport sector, SO 2 emissions are reduced, but changes in NOx emissions depend on the substitution pattern and technology. The effects of replacing gasoline with ethanol and biodiesel also depend on engine features. Biodiesel can have higher NOx emissions than petroleum diesel in traditional direct-injected diesel engines that are not equipped with NOx control catalysts [ 125 ]. This is why no NOx avoided emissions have been taken into account. A 50 % average SO 2 emissions reduction is however considered, as the avoided emissions will depend very much on the blend.
Please find below de corresponding functions:
F 2 = 9.78 SH + 9.78 WPP + 9.44 PV + 9.27 BT I + 9.27 BT H + 9.27 BT HE + 9.27 BT C + 8.9 MSW + 9.38 BEG + 2.7 LBF A + 2.7 LBF T
F 3 = 0.028 SH + 0.028 WPP + 0.026 PV + 0.02 BT I + 0.02 BT H + 0.02 BT HE + 0.02 BT C + 0.028 MSW + 0.02 BEG
F 4 = 0.04126 SH + 0.0407 WPP + 0.038 PV + 0.041 BT I + 0.041 BT H + 0.041 BT HE + 0.041 BT C + 0.04128 MSW + 0.041 BEG + 0.0058 LBF A + 0.0058 LBF T
Based on the typical capital cost ranges for RE power generation technologies, USD/kW [ 49 , 137 – 139 ], the overnight capital cost is calculated (USD/toe) so that the appropriate coefficients can be applied:
F 5 = 0.08 SH + 0.32 WPP + 0.3 PV + 0.18 BT I + 0.14 BT H + 0.18 BT HE + 0.14 BT C + 0.48 MSW + 0.55 BEG + 0.94 LBF A + 0.94 LBF T
It must be noted that a CHP use has been assumed for MSW biogas plants and LBF production.
See below Table
12
, where the precedence constraints have been evaluated by the authors as per the below mentioned subjects, based on the indicated references.
P and SH SW B PV LBF MSW Identified ad hoc applications 5 4 5 5 5 1 Low overnight capital cost/unnecessary donor support 2 3 5 1 1 1 Low maintenance cost 4 5 4 5 1 1 Unnecessary maintenance contract 4 1 5 4 1 1 Long lasting systems 5 4 4 4 4 5 Short distance from energy source 4 5 5 5 2 1 Safe from being stolen in rural environment 4 4 3 1 5 5 Low rural environmental impact 3 5 2 5 2 2 Predictability 4 2 4 2 4 5 Batteries not required 2.5 1 2.5 1 2.5 2.5 AC 2.5 2.5 2.5 1 2.5 2.5 Possible rural modularity 1 2.5 1 2.5 1 1 Added benefits for rural development 1 1 1 1 1 2.5 In-country development 5 3 3 1 5 5 Low LEC 4 4 3 1 1 1 Space efficiency for rural Environment 1 4 1 3 1 1 Low waste generation 2.5 s 2.5 1 2.5 2.5 1Table 12
M and N are then calculated as per Eqs. (
23
) and (
24
) (see Table
13
below):
Calculation of
N
and
M
factors Alternative Coefficient P and SH 4.1 × 106 4.8 × 107 2.5 SW 6.2 × 106 3.6 × 107 2.5 B 6.6 × 106 1.35 × 107 2 PV 4.6 × 107 4 × 105 2 LBF 2 × 108 105 1.5 MSW 3.3 × 108 19,531 1Table 13
Once the coefficients are applied, this is the final equation for F 6 :
F 6 = 2.5 SH + 2.5 WPP + 2 PV + 2 BT I + 2 BT H + 2 BT HE + 2 BT C + MSW + 2 BEG + 1.5 LBF A + 1.5 LBF T
Please find below Table
14
and Figs.
6
,
7
,
8
,
9
,
10
and
11
, which include the results obtained (in ktoe), using the Chebyshev distance, L∞, following the Anti-Ideal Compromise Programming as previously defined in chapter 2.3; taking into account the below mentioned weights.
Optimization results using Matlab
®
programming tools Weights SH WP PV BTI BTH BTHE BTC MSW BEG LBFA LBFT 1,1,1,1,1,1a 86.7 43.2 3.6 2146.4 1.1 0.4 431.8 62.3 15.1 1 180.1 1,0,0,0,0,0 125.9 75.2 3.6 2148.9 1.2 0.4 432.1 0 15.1 1.8 436.3 5,1,1,1,1,1 109.1 61.7 3.6 2148.9 1.2 0.4 432.1 30.2 15.1 1.5 325.1 0,1,0,0,0,0 125.2 75.9 3.6 2148.9 1.2 0.4 432.1 0 15.1 1.8 436.3 1,5,1,1,1,1 104.4 58.1 3.6 2148.7 1.2 0.4 432.1 37.8 15.1 1.4 300.8 0,0,1,0,0,0 78.3 36.3 3.6 2148.9 1.2 0.4 432.1 86.5 15.1 0.9 114.7 1,1,5,1,1,1 86.7 43.5 3.6 2148.8 1.2 0.4 432.1 70.7 15.1 1.1 173.7 0,0,0,1,0,0 47.3 86 3.6 2148.9 1.2 0.4 432.1 14.5 15.1 1.8 436.3 1,1,1,5,1,1 95.5 50.7 3.6 2148.8 1.2 0.4 432.1 54.4 15.1 1.3 247.1 0,0,0,0,1,0 47.3 8.6 3.6 2109 0 0 427.8 0 15.1 0 0 1,1,1,1,5,1 61.2 20.8 3.6 2121.1 0.4 0.1 429.1 18 15.1 0.4 66.7 0,0,0,0,0,1 125 76.1 3.6 2148.9 1.2 0.4 432.1 0 15.1 1.8 436.3 1,1,1,1,1,5 112.6 64.6 3.6 2148.8 1.2 0.4 432.1 23.5 15.1 1.6 348.3 1,5,5,5,1,1 104.3 58.2 3.6 2148.9 1.2 0.4 432.1 38.4 15.1 1.4 299.1 5,1,1,1,1,5 112.6 64.4 3.6 2148.8 1.2 0.4 432.1 23.6 15.1 1.6 349.7 SH, WP, MSW and LBF
T
variation as per the weights assigned to function 1. Source: own construction SH, WP, MSW and LBF
T
variation as per the weights assigned to function 2. Source: own construction SH, WP, MSW and LBF
T
variation as per the weights assigned to function 3. Source: own construction SH, WP, MSW and LBF
T
variation as per the weights assigned to function 4. Source: own construction SH, WP, MSW and LBF
T
variation as per the weights assigned to function 5. Source: own construction SH, WP, MSW and LBF
T
Variation as per the weights assigned to function 6. Source: own constructionTable 14
Fig. 6

Fig. 7

Fig. 8

Fig. 9

Fig. 10

Fig. 11

The authors have aimed to compare the solution obtained given no special weight to any of the functions: (1,1,1,1,1,1); with the obtained values when only one of the functions is taken into account: for example (1,0,0,0,0,0); and finally with the outcome solution when a special weight has been given to a particular function: for example (5,1,1,1,1,1). This way, the different solutions will clearly show the tendency the variables follow, when a particular function is given more importance than the others. The authors have added two more cases to this list, one giving special importance to the three emissions functions ( F 2 , F 3 , F 4 ), and another one targeting the maximum renewable energy substitution and rural health and education development ( F 1 and F 6 ).
The nominal weights (1,1,1,1,1,1) are considered as the baseline. Once this baseline is obtained, then the other cases will be taken into account to give some special relative importance to any of the six functions or even to address some different weights to be applied if necessary [ 15 , 16 , 23 , 24 ]. The results show that PV and BEG stay at their minimum potential value independently of the chosen weights, while the four biomass variables (BT I , BT H , BT HE and BT C ) reach approximately their maximum potential value, except for the two cases where the economic factor is given a certain weight versus the other functions. This exception is totally expected, as function F 5 will always look for the cheapest solution, i.e., the one implementing less renewable energy substitution. The rest of the variables, SH, WP, MSW LBF A and LBFT do vary, depending on the chosen weights. The first three variables are linked together as per Eq. ( 22 ). This means that any variation in one of them, will therefore affect the other. As can be seen in Figs. 6 , 7 , 8 , 9 , 10 and 11 above, when only one function is optimized, a maximum polarized value is obtained for the different variables. Once all six functions are taking into account, even if a weight 5 is applied to a particular one, the difference from the nominal results [the ones obtained as per (1,1,1,1,1,1)] is less acute, flattening this way the value given to the different variables.
If the individual optimizations [for example: (1,0,0,0,0,0)] are not considered, and the last two cases or also not taken into account, the maximization of the above mentioned variables may be summarized as per Table
15
below.
Maximization of SH, WP, MSW, LBF
A
and LBF
T Renewable energy Reaches maximum value when prioritizing SH WP MSW LBFA LBFTTable 15
The authors have summarized below in Table
16
the advantages of applying this energy planning model to Sri Lanka, and also the potential improvements in Table
17
.
Advantages of SRIME application in Sri Lanka SRIME singularity Advantage for Sri Lanka Multi-objective (6 equations) Avoiding this way, single-objective financial perspective, which gradually would make SL poorer and more dependent on oil import Takes into account CO2 and also NOx and SO2 Automobiles are very contaminant in SL, NOx is therefore of great importance Maximizing RE SL has proofed to be a fast RE growing country, improving industry in general Health and Education equation Very innovative precedence constraints application, aiming to set a sustainable growth through energy universal access Possibility of applying weights This way planners may choose which either if all objectives may have the same weight or there is a particular equation that must be given a certain priority Pareto optimal solution Assuring the chosen solution is not ‘dominated’ by any of the equations Potential Improvements for SRIME application in Sri Lanka Potential Improvement Advantage Introduction of hybrid systems Very efficient for remote rural materially underdeveloped areas, with highly flexible configurations, and currently undergoing a high level of implementation Equations weights to be decided by an international team of specialists (energy planners, maintenance specialists, policy makers and politicians) including, of course, people from Sri Lanka One of the most important processes of the SRIME is the weights assignation. Although these groups may have different points of view, and sometimes even opposite objectives: consensus is a mustTable 16
Table 17
This paper shows the possibility of using MCDM methods, focusing on a sustainable and renewable energy approach. The resulting energy models give a great level of importance to the human environmental development factors, avoiding, therefore, the purely economic reasoning. These type of models are becoming a common way of choosing global energy plans [ 139 ] or some independent power plants, such as wind farms [ 140 ]. This work has aimed at establishing a potential energy model implementation methodology that may be applicable for developing countries. The Case Study shows that if SRIME was implemented in Sri Lanka, SH, WP, MSW and LBF T would be specially benefited from the Pareto optimization, while PV and BEG would stay at their official future expected value [ 20 ], having no growth at all. The SRIME model could be relatively easily interpolated to other Asian tropical countries, due to the similar circumstances in terms of health an education low overall parameters, high biomass consumption, monsoon special weather characteristics, low GDP and extremely high petroleum imports dependency.
The authors would like to gratefully acknowledge the support received from Carlos Molina-Dafauce. The authors would also like to thank professors Carlos Romero, Pedro Linares, Cristina Pascual, José L. Hernanz, Inés Izquierdo, and investigator Eder Falcón.
The authors declare no conflict of interest